Introduction
The Gurgaon-Pataudi-Rewari National Highway (NH-352W) is now the 43-kilometer section receiving infrastructure and real estate attention in the NCR region. The National Highways Authority of India (NHAI) has stated that the project is expected to be completed by March 2025, with 60% of the work already completed by late 2024.
If you’re exploring more in the Gurugram belt, check Plotted Development in Sonipat

Project Timeline and Current Status
- The highway was proposed in 2018 in order to upgrade a two-lane state road to a four-lane national highway. The projected cost of the project is around ₹900–1,000 crore.
- Construction started in November 2021, considerably delayed from its initial December 2022 deadline.
- As of September 2024, 60% of the work had been completed. The Wazirpur–Rewari section is expected to be completed by December, while the Dwarka Expressway–Wazirpur section is to be completed by early 2025.
Recent Developments & Delays
- According to an April 2025 update, it appears that the timelines are being pushed back just a bit, now aiming for completion in December 2025 rather than March.
- Construction progress is getting uneven. It is still being delayed by a stormwater drain near sectors 88A–88B in Gurgaon, causing a delay in the construction of service road, which the NHAI has asked GMDA to assist with.
- However, we also still see work on key items like the 180-meter flyover connecting the Dwarka Expressway to NH-352W, providing improved access for Delhi-Gurgaon traffic heading toward Rewari
Implications for Real Estate Growth
- Once NH-352W is finished, there will be huge potential for real estate in Pataudi and Rewari, with even more impact in Gurgaon.
- Real estate corridors should see incredible appreciation, like Pataudi Road, driven by improved connectivity, industrial development, and enhanced commuting access.
| Timeline | Target Milestone / Update |
|---|---|
| 2018 | Project launched |
| Nov 2021 | Construction begins |
| Dec 2022 | Original completion goal (missed) |
| Sep 2024 | 60% of work completed; Wazirpur–Rewari by Dec expected |
| Mar 2025 | Revised target for full completion |
| Apr 2025 | New estimate suggests Dec 2025 completion |
| 2025 – Ongoing | Remaining sections, including service roads, in progress |
| Conclusion | Project timeline extended, with Dec 2025 as the new completion goal |
Conclusion
The Gurgaon–Pataudi–Rewari Highway (NH-352W) is progressing well. Several stretches are expected to be operational by early 2025, and completed by end of the year. The highway is also expected to be a big agent of growth for real estate in NCR.
For investors and developers this is a key time as areas close to the highway, particularly around Pataudi are seeing demand for plotted development, township development or logistics developments. If you want a comprehensive analysis of the investment areas along NH-352W, I’m happy to help!